Biogas CHP-plant Schleswig 1169 kWel

  • Overview

    Expansion of the biogas plant in Schleswig by an aditional CHP-plant. The new gas engine CHP-plant included all auxiliaries was installed into the existing machine hall. The existing Jenbacher system is since the commissioning of the new MTU on standby or is used for peak load operation for the public utility Schleswig. GTP delivered the whole plant engineering concept and prepared all orders for components and supplier services. On the client’s request the acquisition of all components was divided between the client and GTP. In the end the construction supervision including the commissioning was taken over entirely by GTP.

  • Project data

    Location Schleswig, Germany
    Genset type MTU 12V4000L62
    Fuel Biogas
    Electrical output 1169 kW
    Thermal output Water 90/70°C
    Scope of supply engineering services
    components design
    components supply
    plant construction
    project supervision